Building owners who have never seen an overlay go down often picture something like a paint-on coating or a tarp. It is neither. A metal roof overlay is an engineered three-layer roof built on top of the existing sheeting, and the installation follows the same discipline as any other commercial waterproofing project. This is what happens, in order.
Before anyone gets on the roof
The job starts with the assessment that decides whether the roof is a candidate (our 10-point check covers what we look for). From that we produce a build-up specification, a penetration schedule, a drainage layout and a fixed proposal. Access, edge protection and staging are planned with the building manager so the site keeps operating.
Step 1: Preparation
Loose debris, failed sealants and any rusted-through or damaged sheets are dealt with first. Damaged sheets are replaced; surface rust is not a problem because the sheeting is being sealed and covered. Existing fixings are checked and any that are loose or missing are replaced so the substrate is stable.
Step 2: Vapour barrier
A vapour control layer is laid directly over the metal sheeting and sealed at the laps and edges. Its job is to stop warm, moist air from inside the building migrating up into the insulation and condensing against the underside of the membrane. On an occupied building this layer is what keeps the new roof dry from below as well as above.
Step 3: Insulation boards
Rigid insulation boards are laid over the vapour barrier and mechanically fixed through to the purlins. The boards do three things at once: they bridge the profile of the old sheeting to create a flat, continuous deck, they provide thermal insulation across the whole roof rather than just between purlins, and they give the membrane a stable base. Where the original roof has minor ponding, tapered boards correct the falls.
Step 4: PVC membrane
A single-ply PVC membrane is rolled out over the insulation and fixed in the seams, then every seam is hot-air welded. The result is one continuous waterproof layer with no lapped joints and no fixings passing through it. PVC membranes are lightweight, UV-stable and resistant to chemicals and ponding water, which is why they carry warranties of 20 to 30 years and a service life beyond that. If you want to understand how membrane life compares with other systems, read how long waterproofing lasts.
Step 5: Detailing
This is the part that decides whether the roof works. Every upstand, parapet, box gutter, outlet, air conditioning plinth, vent, skylight and pipe is detailed with pre-formed corners, welded flashings and clamped terminations. Outlets are fitted with membrane-compatible drains. Penetrations that cannot be lifted are flashed and welded in place. Our supervisors photograph each detail as it is completed.
Step 6: Testing and inspection
Seams are probe-tested for weld integrity and outlets and low points are checked under water. Hold-point inspections are recorded as the work progresses so the documentation exists before the crew leaves site, not after.
Step 7: Handover
You receive the warranty certificate, the photographic record of the works, the as-built details and an optional maintenance plan. Because the membrane is exposed, inspecting it in future is straightforward: walk the roof, check the outlets and look at the terminations.
How long it takes
A typical warehouse or commercial roof takes three to six weeks depending on size, the number of penetrations and weather. The building stays weather-tight the whole time because the old roof is never removed, so a wet week delays the programme rather than putting the interior at risk.