Two Australian Standards cover waterproofing in buildings. AS 3740 deals with wet areas inside the building, such as bathrooms and laundries. AS 4654 deals with external above-ground waterproofing, which is where balconies, terraces, podiums and roofs sit. If you own, manage or build apartments in Australia, AS 4654 is the document your balconies are judged against. We give an overview of both in our guide to Australian waterproofing standards; this article focuses on what AS 4654 means for a balcony.
The two parts of AS 4654
AS 4654.1 covers the materials: what a membrane has to achieve in terms of elongation, adhesion, resistance to ponding water and UV, and how it is tested. It is the part manufacturers certify against.
AS 4654.2 covers design and installation: how the membrane is detailed, how high it goes, how the balcony drains, and how junctions, penetrations and thresholds are treated. It is the part contractors and certifiers work to, and the part most balcony defects breach.
The requirements that decide whether a balcony leaks
Membrane height at walls. The membrane must extend up any adjoining wall to a minimum height above the finished surface, so that water sitting on the balcony cannot get behind it. Membranes that stop at tile level are one of the most common defects we find.
Door thresholds. There must be a step-down from the internal floor to the external finished surface, and the membrane must be carried up and over or behind the threshold so that water driven against the door cannot pass under it. Level thresholds are possible but need a specific drainage detail to comply.
Falls. The balcony must fall to the drainage outlet at a minimum gradient so water does not pond. This is delivered by the screed or the slab itself, and it is checked before the membrane goes down.
Drainage outlets and overflows. Outlets must be at the low point, the membrane must be dressed into the outlet flange, and an overflow is required so that a blocked drain does not flood the unit.
Bond breakers and movement. Every internal corner where floor meets wall needs a bond breaker so the membrane can flex across the joint without tearing. Movement joints in the slab must be carried through the membrane and the finishes.
Penetrations. Balustrade posts, pipes and fixings passing through the membrane must be sleeved, flashed and sealed. Posts core-drilled after waterproofing without reinstating the membrane are a clear breach.
Protection of the membrane. Membranes under tiles need a protection layer or drainage cell so that screeding and tiling do not damage them, and so water that gets through the tiles can drain.
What compliance looks like in practice
Compliance is demonstrated by the installation, not the product. A membrane certified to AS 4654.1 applied without bond breakers, too thin, or stopped short of the threshold does not comply with AS 4654.2. Hold-point inspections, flood testing before the finishes go down, and a photographic record are how a contractor shows the work meets the standard, and how a body corporate protects itself if a defect claim arises later.
In New South Wales the work must also be done by a licensed waterproofer, and on new residential buildings the certifier will expect evidence of both the licence and the inspections.
If your balcony was built before the current standard
Many balconies built in the 1990s and 2000s predate the current edition of AS 4654.2 or were built without following it. They are not automatically defective, but when they leak the repair should bring them up to the current requirements rather than replicate the original mistake. Our article on why balconies leak and how to fix them walks through what that repair involves, and our balcony waterproofing service page covers how we approach it.
Ask before the tiles go down
If you are specifying a balcony repair or new work and want the detailing checked against AS 4654 before it is covered up, we can review the design or inspect the work at the hold points. Contact Danrae Group or call 1800 326 723.